[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109849,783,1,"单选题","下列选项中，不属于在动态的投资控制过程中应着重做好的工作的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对计划目标值的论证和分析",false,{"key":16,"text":17,"correct":18},"B","明确项目投资控制者及其任务",true,{"key":20,"text":21,"correct":14},"C","采取控制措施以确保投资控制目标的实现",{"key":23,"text":24,"correct":14},"D","进行项目计划值与实际值的比较，以判断是否存在偏差","2020版教材P3-4 在这一动态控制过程中，应着重做好以下几项工作： (1) 对计划目标值的论证和分析。 (2) 及时对项目进展做出评估，即收集实际数据。 (3) 进行项目计划值与实际值的比较，以判断是否存在偏差。 (4) 采取控制措施以确保投资控制目标的实现。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]