[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109848,783,1,"单选题","建设项目投资决策后，投资控制的关键阶段是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计阶段",true,{"key":16,"text":17,"correct":18},"B","施工招标阶段",false,{"key":20,"text":21,"correct":18},"C","施工阶段",{"key":23,"text":24,"correct":18},"D","竣工阶段","投资控制贯穿于项目建设的全过程。从该图可看出，影响项目投资最大的阶段，是约占工程项目建 设周期四分之一的技术设计结束前的工作阶段。在初步设计阶段，影响项目投资的可能性为 75%～95%； 在技术设计阶段，35%～75%；在施工图设计阶段，5%～35%。很显然，项目投资控制的重点在于施工以 前的投资决策和设计阶段，而在项目做出投资决策后，控制项目投资的关键就在于设计。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]