[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109847,783,1,"单选题","建设工程项目技术设计和施工图设计应依据()设置投资控制目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算",false,{"key":16,"text":17,"correct":18},"B","设计概算",true,{"key":20,"text":21,"correct":14},"C","施工图预算",{"key":23,"text":24,"correct":14},"D","工程量清单","目标的设置应是很严肃的，应有科学的依据。 投资控制目标的设置应是随着工程项目建设实践的不断深入而分阶段设置，具体来讲，投资估算应 是建设工程设计方案选择和进行初步设计的投资控制目标；设计概算应是进行技术设计和施工图设计的 投资控制目标；施工图预算或建安工程承包合同价则应是施工阶段投资控制的目标。 有机联系的各个阶段目标相互制约，相互补充，前者控制后者，后者补充前者",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]