[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109846,783,1,"单选题","项目监理机构施工阶段投资控制采取的措施中，属于经济措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制设计变更",false,{"key":16,"text":17,"correct":18},"B","编制资金使用计划",true,{"key":20,"text":21,"correct":14},"C","编制投资控制工作计划",{"key":23,"text":24,"correct":14},"D","优化设计节约投资","本题考查的是投资控制的措施。经济措施：（1）编制资金使用计划，确定、分解投资控制目标。对工程项目造价目标进行风险分析，并制定防范性对策。（2）进行工程计量。（3）复核工程付款账单，签发付款证书。（4）定期进行投资实际支出值与计划目标值的比较；发现偏差，分析产生偏差的原因，采取纠偏措施。（5）协商确定工程变更的价款。审核竣工结算。（6）对工程施工过程中的投资支出做好分析与预测，经常或定期向建设单位提交项目投资控制及其存在问题的报告。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]