[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109845":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109845,783,1,"单选题","某项目，建安工程费1000万元，设备及工器具购置费2000万元，工程建设其他费用300万元，基本预备费160万元，建设期间国家新批准税种的税额45万元，建设期贷款利息60万元，涨价预备费80万元，流动资金800万元。则该项目的固定资产投资为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3520",false,{"key":16,"text":17,"correct":14},"B","3540",{"key":19,"text":20,"correct":21},"C","3600",true,{"key":23,"text":24,"correct":14},"D","4400","固定资产投资=静态投资+动态投资=（2000+1000+300+160）+（60+80）=3600",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]