[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109837,783,1,"单选题","非生产性建设工程项目总投资包括（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","括建设投资、建设期利息和流动资金",false,{"key":16,"text":17,"correct":14},"B","建设投资和流动资金",{"key":19,"text":20,"correct":21},"C","固定资产投资",true,{"key":23,"text":24,"correct":14},"D","建安工程费、工程建设其他费、预备费、建设期利息和流动资金","2020版教材P1-2 生产性建设工程项目总投资包括建设投资、建设期利息和流动资金三部分；非生产性建设工程项目总投资包括建设投资和建设期利息两部分。其中建设投资和建设期利息之和对应于固定资产投资。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]