[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109834,783,1,"单选题","在某建设项目投资构成中，建筑安装工程费为2000万元，设备及工器具购置费为1000万元，工程建设其他费用为500万元，预备费为200万元，建设期贷款1800万元，应计利息为80万元，流动资金贷款400万元，则该建设项目的建设投资为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5980",false,{"key":16,"text":17,"correct":14},"B","5580",{"key":19,"text":20,"correct":14},"C","3780",{"key":22,"text":23,"correct":24},"D","3700",true,"2020版教材P1-2 建设投资，由设备及工器具购置费、建筑安装工程费、工程建设其他费用、预备费(包括基本预备费和涨价预备费)组成。则该项目的建设投资=2000+1000+500+200=3700(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]