[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109830,783,1,"单选题","某项目建筑安装工程费为1000万元，设备工器具购置费为700万元，工程建设其他费为500万元，基本预备费为100万元，涨价预备费为150万元，建设期利息为60万元，则该项目的静态投资为 ( )万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2200",false,{"key":16,"text":17,"correct":18},"B","2300",true,{"key":20,"text":21,"correct":14},"C","2450",{"key":23,"text":24,"correct":14},"D","2510","2020版教材P1-2 固定资产投资可分为静态投资部分和动态投资部分。静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的固定资产投资增加额，包括涨价预备费和建设期利息。 该项目的静态投资=1000+700+500+100=2300万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]