[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109823,783,1,"单选题","在建设投资中，()属于动态投资部分",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",false,{"key":16,"text":17,"correct":18},"B","建设期利息",true,{"key":20,"text":21,"correct":14},"C","设备运杂费",{"key":23,"text":24,"correct":14},"D","铺底流动资金","固定资产投资可分为静态投资部分和动态投资部分。 静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。 动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期 价格变动引起的建设投资增加额，包括涨价预备费和建设期利息",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]