[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109821,783,1,"单选题","某项目，建安工程费3000万元，设备工器具购置费4000万元，工程建设其他费用600万元，建设期利息200万元，铺底流动资金160万元，建设期间主要税种的税额45万元，则该项目的静态投资为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7000",false,{"key":16,"text":17,"correct":18},"B","7600",true,{"key":20,"text":21,"correct":14},"C","7700",{"key":23,"text":24,"correct":14},"D","7805","本题考查的是建设工程项目投资的概念。固定资产投资可分为静态投资部分和动态投资两个部分；其中，静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费构成。因此，该项目的静态投资（部分）＝3000＋4000＋600＝7600（万元）。动态投资部分包括涨价预备费和建设期利息。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]