[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109820,783,1,"单选题","（2020年真题）某产品4个功能区的功能指数和现实成本如下表。若产品总成本保持不变，以成本改进期望值为依据，则应优先作为价值工程改进对象的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","F1",false,{"key":16,"text":17,"correct":18},"B","F2",true,{"key":20,"text":21,"correct":14},"C","F3",{"key":23,"text":24,"correct":14},"D","F4","P102-111 V\u003C1。即功能现实成本大于功能评价值。表明评价对象的现实成本偏高，而功能要求不高。这时，一种可能是由于存在着过剩的功能，另一种可能是功能虽无过剩，但实现功能的条件或方法不佳，以致使实现功能的成本大于功能的实际需要。这两种情况都应列入功能改进的范围，并且以剔除过剩功能及降低现实成本为改进方向，使成本与功能比例趋于合理。根据上表应优先作为价值工程改进对象的是F2。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]