[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109806,783,1,"单选题","施工图预算审查时，利用房屋建筑工程标准层建筑面积数对楼面找平层、天棚抹灰等工程量进行审查的方法，属于（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分组计算审查法",true,{"key":16,"text":17,"correct":18},"B","重点审查法",false,{"key":20,"text":21,"correct":18},"C","筛选审查法",{"key":23,"text":24,"correct":18},"D","对比审查法","2020版教材P125-128 分组计算审查法就是把预算中有关项目按类别划分若干组，利用同组中的一组数据审查分项工程量的一种方法。这种方法首先将若干分部分项工程按相邻且有一定内在联系的项目进行编组，利用同组分项工程间具有相同或相近计算基数的关系，审查一个分项工程数，由此判断同组中其他几个分项工程的准确程度。如一般的建筑工程中将底层建筑面积可编为一组。先计算底层建筑面积或楼(地)面面积，从而得知楼面找平层、天棚抹灰的工程量等，依次类推。该方法特点是审查速度快、工作量小。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]