[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109803":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109803,783,1,"单选题","采用定额单价法计算工程费用时，若分项工程施工工艺条件与定额单价不一致而造成人工、机械的数量增减时，对定额的处理方法一般是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制补充单价表",false,{"key":16,"text":17,"correct":14},"B","直接套用定额单价",{"key":19,"text":20,"correct":21},"C","调量不换价",true,{"key":23,"text":24,"correct":14},"D","按实际价格换算定额单价","2020版教材P120-125 对于定额单价法，分项工程施工工艺条件与预算单价或单位估价表不一致而造成人工、机械的数量增减时， 一般调量不换价。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]