[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109802":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109802,783,1,"单选题","用实物量法编制施工图预算，有关人工、材料和施工机械台班的单价，采用的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算定额手册中的价格",false,{"key":16,"text":17,"correct":18},"B","当时当地的实际市场价格",true,{"key":20,"text":21,"correct":14},"C","协会公布的平均价格",{"key":23,"text":24,"correct":14},"D","政府指导价格","2020教材P120-125 实物量法中计算并汇总人工费、材料费、机具使用费，是根据当时当地工程造价管理部门定期发布的或企业根据市场价格确定的人工工资单价、材料预算价格、施工机具台班单价分别乘以人工、材料、机具消耗量，汇总即为单位工程人工费、材料费和施工机具使用费。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]