[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109799,783,1,"单选题","当初步设计达到一定深度，建筑结构比较明确时，可采用（）编制建筑工程概算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扩大单价法",true,{"key":16,"text":17,"correct":18},"B","生产能力指标法",false,{"key":20,"text":21,"correct":18},"C","实物量法",{"key":23,"text":24,"correct":18},"D","预算单价法","2020教材P113-115 编制建筑单位工程概算一般有扩大单价法、概算指标法两种，可根据编制条件、依据和要求的不同适当选取。 采用扩大单价法编制建筑工程概算比较准确，但计算较繁琐。在套用扩大单位估价表时，若所在地区的工资标准及材料预算价格与概算定额不符，则需要重新编制扩大单位估价或测定系数加以修正。当初步设计达到一定深度、建筑结构比较明确时，可采用这种方法编制建筑工程概算。 由于设计深度不够等原因，对一般附属、辅助和服务工程等项目，以及住宅和文化福利工程项目或投资比较小、比较简单的工程项目，可采用概算指标法编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]