[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109795,783,1,"单选题","施工图预算审查方法中，审查质量高、效果好但工作量大的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准预算审查法",false,{"key":16,"text":17,"correct":14},"B","重点审查法",{"key":19,"text":20,"correct":21},"C","逐项审查法",true,{"key":23,"text":24,"correct":14},"D","对比审查法","2020教材P125-128 逐项审查法又称全面审查法，即按定额顺序或施工顺序，对各项工程细目逐项全面详细审查的一种方法。其优点是全面、细致，审查质量高、效果好。缺点是工作量大，时间较长。这种方法适合于一些工程量较小、工艺比较简单的工程。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]