[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109793,783,1,"单选题","当初步设计有详细设备清单时，编制设备安装工程概算精确性较高的方法是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","扩大单价法",false,{"key":16,"text":17,"correct":14},"B","概算指标法",{"key":19,"text":20,"correct":14},"C","修正概算指标法",{"key":22,"text":23,"correct":24},"D","预算单价法",true,"2020教材P113-115 设备安装工程概算编制的基本方法有： (1) 预算单价法。当初步设计有详细设备清单时，可直接按预算单价(预算定额单价)编制设备安装工程概算。根据计算的设备安装工程量，乘以安装工程预算单价，经汇总求得。 用预算单价法编制概算，计算比较具体，精确性较高。 (2) 扩大单价法。当初步设计的设备清单不完备，或仅有成套设备的重量时，可采用主体设备、成套设备或工艺线的综合扩大安装单价编制概算。 (3) 概算指标法。当初步设计的设备清单不完备，或安装预算单价及扩大综合单价不全，无法采用预算单价法和扩大单价法时，可采用概算指标编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]