[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109780,783,1,"单选题","实物量法编制施工图预算所用的材料单价应采用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","网上咨询厂家的报价",false,{"key":16,"text":17,"correct":14},"B","编制预算定额时采用的单价",{"key":19,"text":20,"correct":21},"C","当时当地的实际价格",true,{"key":23,"text":24,"correct":14},"D","预算定额中采用的单价加上运杂费","实物量法编制施工图预算所用人工、材料和机械台班的单价都是当时当地的实际价格。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]