[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109773":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109773,783,1,"单选题","采用定额单价法编制施工图预算时，如果分项工程的某一种主要材料品种与预算单价或单位估价表中规定材料不一致时，该分项工程单价的确定方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按实际使用材料价格换算预算单价",true,{"key":16,"text":17,"correct":18},"B","直接套用同类材料的预算单价",false,{"key":20,"text":21,"correct":18},"C","调整工程量而不换算预算单价",{"key":23,"text":24,"correct":18},"D","编制补充单位估价表","不一致时，我们用“换”。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]