[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109758,783,1,"单选题","当初步设计的设备清单不完备，或仅有成套设备的重量时，应优先采用（ ）编制设备安装工程概算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合扩大单价法",true,{"key":16,"text":17,"correct":18},"B","概算指标法",false,{"key":20,"text":21,"correct":18},"C","修正概算指标法",{"key":23,"text":24,"correct":18},"D","预算单价法","初步设计的设备清单不完备，或仅有成套设备的重量时，可采用主体设备，成套设备或工艺线的综合扩大安装单价编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]