[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109754,783,1,"单选题","关于设计概算的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计概算是确定和控制建设工程项目全部投资的文件",false,{"key":16,"text":17,"correct":18},"B","编制设计概算不需考虑建设项目施工条件对投资的影响",true,{"key":20,"text":21,"correct":14},"C","如果设计概算值超过投资建设额，必须修改设计或重新立项审批",{"key":23,"text":24,"correct":14},"D","设计概算由设计单位负责编制，并对其编制质量负责","编制设计概算需考虑建设项目施工条件对投资的影响，见P113。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]