[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109751,783,1,"单选题","采用强制确定法对某工程四个分部工程进行价值工程对象的选择，各分部工程的功能系数和成本系数见下表。 根据计算，应优先选择分部工程（ ）为价值工程对象。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","甲",false,{"key":16,"text":17,"correct":14},"B","乙",{"key":19,"text":20,"correct":14},"C","丙",{"key":22,"text":23,"correct":24},"D","丁",true,"本题考查的是价值工程应用。 甲的价值系数=0.345÷0.270=1.28 乙的价值系数=0.210÷0.240=0.88 丙的价值系数=0.311÷0.270=1.15 丁的价值系数=0.134÷0.220=0.61 通过上面的计算可知应选用丁作为价值工程对象。 V＜1，目前所占的成本偏高，从而会导致该对象的功能过剩。应将评价对象列为改进对象，改善方向主要是降低成本。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]