[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109732,783,1,"单选题","（2020年真题）某实行招标的工程，招标文件与中标人投标文件中的合同价款不一致时，签订书面合同时确定合同价款应以（ ）为准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有利于招标人的约定",false,{"key":16,"text":17,"correct":14},"B","招标人和投标人重新谈判的结果",{"key":19,"text":20,"correct":21},"C","中标人投标文件",true,{"key":23,"text":24,"correct":14},"D","招标文件","P151-154 合同约定不得违背招标、投标文件中关于工期、造价、质量等方面的实质性内容。招标文件与中标人投标文件不一致的地方应以投标文件为准。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]