[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109730,783,1,"单选题","（2020年真题）根据《建设工程工程量清单计价规范》，编制招标控制价时，总承包服务费应按照（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","省级或行业建设主管部门规定或参考相关规范",true,{"key":16,"text":17,"correct":18},"B","国家统一规定或参考相关规范",false,{"key":20,"text":21,"correct":18},"C","工程所在地同类项目总承包服务费平均水平",{"key":23,"text":24,"correct":18},"D","招标控制价编制单位咨询潜在投标人的报价人","P139-140 编制招标控制价时，总承包服务费应按照省级或行业建设主管部门的规定计算，或参考相关规范计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]