[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109728,783,1,"单选题","（2019年真题）某工程施工过程中发生了一项未在合同中约定的零星工作，增加费用2万元，此费用应列入工程的（ ）中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","暂估价",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","总承包服务费","本题考查的是工程量清单编制。计日工是为了解决现场发生的零星工作的计价而设立的。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]