[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109724,783,1,"单选题","（2017年真题）采用固定总价合同时，发包方承担的风险是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实物工程量变化",false,{"key":16,"text":17,"correct":14},"B","工程单价变化",{"key":19,"text":20,"correct":14},"C","工期延误",{"key":22,"text":23,"correct":24},"D","工程范围变更",true,"本题考查的是合同计价方式。采用这种合同，合同总价只有在设计和工程范围发生变更的情况下才能随之作相应的变更，除此之外，合同总价一般不得变动。采用固定总价合同，承包方要承担合同履行过程中的主要风险，黑钻压卷，金考典软件考前一周更新，下载链接 www.jinkaodian.com 要承担实物工程量、工程单价等变化而可能造成损失的风险。所以发包方承担的风险只有工程范围变更带来的风险。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]