[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109722,783,1,"单选题","（2015年真题）采用估算工程量单价合同时，最后的工程结算总价是按（ ）计算确定的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人提供的估计工程量及承包人所填报的单价",false,{"key":16,"text":17,"correct":14},"B","发包人提供的估计工程量及承包人实际发生的单价",{"key":19,"text":20,"correct":21},"C","实际完成的工程量及承包人所填报的单价",true,{"key":23,"text":24,"correct":14},"D","实际完成的工程量及承包人实际发生的单价","本题考查的是合同计价方式。最后的工程结算价应按照实际完成的工程量来计算，即按合同中的分部分项工程单价和实际工程量，计算得出工程结算和支付的工程总价格。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]