[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109721,783,1,"单选题","某招标工程按《建设工程工程量清单计价规范》(GB50500—2003)编制工程量清单，其中分部分项工程量清单的项目编码十至十二位应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按附录的规定设置",false,{"key":16,"text":17,"correct":14},"B","按规定的统一项目编码编制",{"key":19,"text":20,"correct":21},"C","由清单编制人设置",true,{"key":23,"text":24,"correct":14},"D","由投标人自001起顺序编制","2020教材P130-133 项目编码十至十二位应根据拟建工程的工程量清单项目名称和项目特征设置，同一招标工程的项目编码不得有重码。故选项A、B错误。 招标工程的分部分项工程量清单由清单编制人（一般为招标人）编制，故选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]