[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109720,783,1,"单选题","根据《建设工程量清单计价规范》（GB50500－2013）编制的工程量清单中，某分部分项工程的项目编码010302004005，则“01”的含义是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分项工程顺序码",false,{"key":16,"text":17,"correct":14},"B","分部工程顺序码",{"key":19,"text":20,"correct":21},"C","专业工程码",true,{"key":23,"text":24,"correct":14},"D","附录分类顺序码","2020版教材P130-133 在十二位数字中，一至二位为专业工程码，三至四位为附录分类顺序码；五至六位为分部工程顺序码；七、八、九位为分项工程项目名称顺序码；十至十二位为清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]