[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109715,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500—2013的规定，项目编码中的第二级顺序码指的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业工程码",false,{"key":16,"text":17,"correct":18},"B","附录分类顺序码",true,{"key":20,"text":21,"correct":14},"C","分部工程顺序码",{"key":23,"text":24,"correct":14},"D","分项工程项目名称顺序码","2020教材P130-133 《建设工程工程量清单计价规范》规定，一至二位为专业工程码；三至四位为附录分类顺序码；五至六位为分部工程顺序码；七、八、九位为分项工程项目名称顺序码；十至十二位为清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]