[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109713,783,1,"单选题","在纯单价合同中工程结算时的工程量应以招标人或由其授权委托的监理工程师核准的（）为依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","清单中的工程量",false,{"key":16,"text":17,"correct":14},"B","预算工程量",{"key":19,"text":20,"correct":21},"C","实际完成量",true,{"key":23,"text":24,"correct":14},"D","计划完成量","2020教材P146-151 采用纯单价合同时，发包方只向承包方给出发包工程的有关分部分项工程以及工程范围，不对工程量作任何规定。即在招标文件中仅给出工程内各个分部分项工程一览表、工程范围和必要的说明，而不必提供实物工程量。承包方在投标时只需要对这类给定范围的分部分项工程做出报价即可，合同实施过程中按实际完成的工程量进行结算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]