[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109712,783,1,"单选题","关于投标报价与招标控制价的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两者均为期望价格",false,{"key":16,"text":17,"correct":18},"B","投标报价高于招标控制价的应予废标",true,{"key":20,"text":21,"correct":14},"C","招标控制价是投标报价的成本价",{"key":23,"text":24,"correct":14},"D","开标时招标控制价可根据投标报价上下浮动","2020教材P139-140 选项A错误，投标报价是投标人对拟建工程的期望价格。招标控制价是招标人编制的招标工程的最高投标限价。 选项B正确，投标人的投标报价高于招标控制价的应予废标。 选项C错误，招标控制价是投标报价的最高投标限价。 选项D错误，招标人应在招标文件中如实公布招标控制价，不得对所编制的招标控制价进行上浮或下调。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]