[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109710,783,1,"单选题","分部分项工程量清单项目编码设为五级，其中第三级表示的是( )顺序码。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业工程",false,{"key":16,"text":17,"correct":18},"B","分部工程",true,{"key":20,"text":21,"correct":14},"C","分项工程",{"key":23,"text":24,"correct":14},"D","工程量清单","2020教材P130-133",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]