[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109709,783,1,"单选题","采用工程量清单方式招标时，由( )负责工程量清单的准确性和完整性。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人",true,{"key":16,"text":17,"correct":18},"B","投标人",false,{"key":20,"text":21,"correct":18},"C","评标委员会",{"key":23,"text":24,"correct":18},"D","监理单位","2020教材P130-133 工程量清单应由具有编制能力的招标人或受其委托，具有相应资质的工程造价咨询人编制。采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]