[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109705,783,1,"单选题","在工程量清单计价模式下，关于确定分部分项工程项目综合单价的说法，正确的是 ( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","若分部分项工程量清单项目特征的描述与设计图纸不符，投标人应按设计图纸确定综合单价",false,{"key":16,"text":17,"correct":14},"B","综合单价中不需考虑招标文件中要求投标人承担的风险费用",{"key":19,"text":20,"correct":14},"C","综合单价中应考虑招标人和投标人承担的所有风险费用",{"key":22,"text":23,"correct":24},"D","招标工程量清单中提供了暂估单价的材料，按暂估的单价进入综合单价",true,"2020教材P141-146 选项A错误，在招标投标过程中，当出现招标工程量清单特征描述与设计图纸不符时，投标人应以招标工程量清单的项目特征描述为准，确定投标报价的综合单价。 选项B、C错误，招标文件中要求投标人承担的风险内容和范围，投标人应将其考虑到综合单价中。 选项D正确，招标工程量清单中提供了暂估单价的材料、工程设备，按暂估的单价进入综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]