[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109701,783,1,"单选题","对于灾后恢复工程，适合采用（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可调总价合同",false,{"key":16,"text":17,"correct":14},"B","纯单价合同",{"key":19,"text":20,"correct":14},"C","可调单价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"2020教材P146-151 在招标过程中，对一些紧急工程，如灾后恢复工程、要求尽快开工且工期较紧的工程等，可能仅有实施方案，还没有施工图纸，因此承包商不可能报出合理的价格。此时，采用成本加酬金合同比较合理。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]