[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109698,783,1,"单选题","一般而言，采用固定总价合同时，承包商的投标报价较高的原因是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包商丧失了今后一切的索赔权利",false,{"key":16,"text":17,"correct":14},"B","业主今后工程款结算的工作量减少而给予承包商的费用补偿",{"key":19,"text":20,"correct":14},"C","业主今后可以增加工程范围和内容而不给予承包商另外的费用补偿",{"key":22,"text":23,"correct":24},"D","承包商会将工程量及一切不可预见因素的风险补偿加到投标报价中",true,"2020教材P146-151 由于承包方可能要为许多不可预见的因素付出代价，所以往往会加大不可预见费用，致使固定总价合同的投标价格偏高。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]