[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109697,783,1,"单选题","下列费用中，不应列入总价措施项目清单的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业工程暂估价",true,{"key":16,"text":17,"correct":18},"B","安全文明施工费",false,{"key":20,"text":21,"correct":18},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","夜间施工增加费","2020教材P133-139 其他项目清单包括暂列金额、暂估价、计日工和总承包服务费。选项BCD属于措施项目费，应列入总价措施项目清单。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]