[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109696,783,1,"单选题","下列关于招标控制价确定方法的说法中，符合《建设工程工程量清单计价规范》GB 50500—2013规定的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","措施项目费中的安全文明施工费根据施工技术方案计价",false,{"key":16,"text":17,"correct":14},"B","措施项目费以项为单位计价的，价格包括除利润、税金以外的全部费用",{"key":19,"text":20,"correct":14},"C","总承包服务费由发承包双方协商确定",{"key":22,"text":23,"correct":24},"D","税金应按国家或省级、行业建设主管部门规定的标准计算",true,"2020教材P139-140 选项A错误，措施项目费中的安全文明施工费应当按照国家或省级、行业建设主管部门的规定标准计价。 选项B错误，措施项目费以项为单位计价的，价格包括除规费和税金以外的全部费用； 选项C错误，编制招标控制价时，总承包服务费应按照省级或行业建设主管部门的规定计算，或参考相关规范计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]