[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109694,783,1,"单选题","当招标人仅要求总包人对其发包的专业工程进行现场协调和统一管理、对竣工资料进行统一汇总整理等服务时，总包服务费按（）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总承包工程估算造价的5％左右",false,{"key":16,"text":17,"correct":14},"B","发包的专业工程估算造价的3％左右",{"key":19,"text":20,"correct":21},"C","发包的专业工程估算造价的1.5％左右",true,{"key":23,"text":24,"correct":14},"D","总承包工程估算造价的1.5％左右","2020教材P139-140 当招标人仅要求总包人对其发包的专业工程进行现场协调和统一管理、对竣工资料进行统一汇总整理等服务时，总包服务费按发包的专业工程估算造价的1.5％左右计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]