[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109693,783,1,"单选题","下列关于工程量清单编制的说法，错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采用工程量清单方式招标的，招标工程量清单的准确性和完整性由招标人负责",false,{"key":16,"text":17,"correct":14},"B","拟定的招标文件应作为工程量清单编制的依据",{"key":19,"text":20,"correct":21},"C","施工现场情况、工程特点及专项施工方案应作为工程量清单编制的依据",true,{"key":23,"text":24,"correct":14},"D","工程量清单的组成中包括规费和税金清单","2020教材P130-133 选项C错误，施工现场情况、地勘水文资料、工程特点及常规施工方案是工程量清单编制的依据。不包括专项施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]