[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109692,783,1,"单选题","可以促使承包方关心和降低成本，缩短工期，而且成本可以随设计的进展而加以调整，实际工程中应用较多的合同计价方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本加固定百分比酬金",false,{"key":16,"text":17,"correct":14},"B","成本加固定金额酬金",{"key":19,"text":20,"correct":21},"C","成本加奖罚",true,{"key":23,"text":24,"correct":14},"D","成本加固定最大酬金","2020教材P146-151 成本加奖罚计价方式可以促使承包方关心和降低成本，缩短工期，而且预期成本可以随着设计的进展加以调整，所以发承包双方都不会承担太大的风险，故这种合同计价方式应用较多。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]