[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109688":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109688,783,1,"单选题","若采用可调总价合同，在合同执行过程中，（ ）发生变化时，可对合同总价进行相应的调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工设备",false,{"key":16,"text":17,"correct":18},"B","工料价格指数",true,{"key":20,"text":21,"correct":14},"C","施工顺序",{"key":23,"text":24,"correct":14},"D","施工方法","2020教材P146-151 可调总价合同的总价一般也是以设计图纸及规定、现行规范为基础，在报价及签约时，按招标文件的要求和当时的物价计算合同总价。但合同总价是一个相对固定的价格，在合同执行过程中，由于通货膨胀而使所用的工料成本增加，可对合同总价进行相应的调整。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]