[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109686,783,1,"单选题","某工程采用固定总价合同，合同执行过程中，在发生（）的情况下，发包方应对合同总价作相应的调整。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包商漏算工程量",false,{"key":16,"text":17,"correct":14},"B","工、料、机价格上涨",{"key":19,"text":20,"correct":21},"C","工程范围调整",true,{"key":23,"text":24,"correct":14},"D","出现恶劣气候","2020教材P146-151 采用固定总价合同，合同总价只有在设计和工程范围发生变更的情况下才能随之作相应的变更，除此之外，合同总价一般不得变动。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]