[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109680":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109680,783,1,"单选题","采用可调总价合同时，发包方承担了()风险。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实物工程量",false,{"key":16,"text":17,"correct":14},"B","成本",{"key":19,"text":20,"correct":14},"C","工期",{"key":22,"text":23,"correct":24},"D","通货膨胀",true,"⒉可调总价合同 合同总价是一个相对固定的价格，在合同执行过程中，由于通货膨胀而使所用的工料成本增加，可对合同总价进行相应的调整。 与固定总价合同的不同之处在于，它对合同实施中出现的风险做了分摊，发包方承担了通货膨胀的风险，而承包方承担合同实施中实物工程量、成本和工期因素等的其他风险。 可调总价合同适用于工程内容和技术经济指标规定很明确的项目，由于合同中列有调值条款，所以工期在1 年以上的工程项目较适于采用这种合同计价方式。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]