[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109673,783,1,"单选题","某施工项目，发包方与承包方按固定总价签订了工程承包合同，合同实施过程中可以对合同总价做相应变更的情况是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通货膨胀带来成本上涨",false,{"key":16,"text":17,"correct":14},"B","定额消耗量变化",{"key":19,"text":20,"correct":14},"C","遇雨季导致工期延长",{"key":22,"text":23,"correct":24},"D","设计变更",true,"2020教材P146-151 采用固定总价合同，合同总价只有在设计和工程范围发生变更的情况下才能随之作相应的变更，除此之外，合同总价一般不得变动。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]