[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109646,783,1,"单选题","采用工程量清单方式招标时，工程量清单的准确性和完整性应由()负责。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制清单的造价工程师",false,{"key":16,"text":17,"correct":14},"B","审核清单的造价工程师",{"key":19,"text":20,"correct":21},"C","工程招标人",true,{"key":23,"text":24,"correct":14},"D","工程造价咨询人","工程量清单应由具有编制能力的招标人或受其委托，具有相应资质的工程造价咨询人编制。采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。 工程量清单由分部分项工程量清单、措施项目清单、其他项目清单、规费项目清单、税金项目清单组成。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]