[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109645,783,1,"单选题","关于编制招标控制价的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","综合单价应包括由招标人承担的费用及风险",false,{"key":16,"text":17,"correct":14},"B","安全文明施工费按投标人的施工组织设计确定",{"key":19,"text":20,"correct":14},"C","措施项目费应为包括规费、税金在内的全部费用",{"key":22,"text":23,"correct":24},"D","暂估价中的材料单价，应按招标工程量清单的单价计入综合单价",true,"暂估价中的材料、工程设备单价、控制价应按招标工程量清单列出的单价计入综合单价。暂估价中专业工程金额应按招标工程量清单中列出的金额填写。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]