[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109625,783,1,"单选题","（2020年真题）在施工过程中发现文物，导致费用增加和工期延误，承包人提出索赔，监理人处理该索赔的正确做法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可批复增加的费用、延误的工期和相应利润",false,{"key":16,"text":17,"correct":14},"B","可批复延误的工期，不批复增加的费用和利润",{"key":19,"text":20,"correct":14},"C","可批复增加的费用，不批复延误的工期和利润",{"key":22,"text":23,"correct":24},"D","可批复增加的费用和延误的工期，不批复利润",true,"P178-184",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]