[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109624,783,1,"单选题","（2020年真题）某土方工程，合同工程量为1万m3，合同综合单价为60元\u002Fm3，合同约定：当实际工程量增加15%以上时，超出部分的工程量综合单价应予调低，施工过程中由于发包人设计变更，实际完成工程量1.3万m3，监理人与承包人依据合同约定协商后，确定的土方工程变更单价为56元\u002Fm3。该土方工程实际结算价款为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","72.80",false,{"key":16,"text":17,"correct":14},"B","76.80",{"key":19,"text":20,"correct":21},"C","77.40",true,{"key":23,"text":24,"correct":14},"D","78.00","P175-178 实际完成工程量1.3万m3＞1*（1+15%）=1.15万m3，超出部分的工程量综合单价应予调低。 该土方工程实际结算价款=1*1.15*60+（1.3-1*1.15）*56=77.4万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]